I have a user who has two boards created using the same filter as the base for the board. One is kanban the other is a scrum board. The epic is showing up in one board and not the other. How do we get it so that the epic appears on both boards?
I updated the filter in the Scrum board to include epics as a issuetype as it wasn't in the list of specific issuetypes the user created. This resolved it and the board is working for the user now.
I assume the epics are not showing up on the Kanban board, correct? For them to show up you need to use the backlog, have a look at Managing epics in Kanban project.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
They are not showing up on the Scrum board actually. They appear on the Kanban board.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Check and see if the Epic Status (different from Status) has been set to Done.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
I updated the filter in the Scrum board to include epics as a issuetype as it wasn't in the list of specific issuetypes the user created. This resolved it and the board is working for the user now.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.