JIRA Agile - how to use other than done field in burn down chart

 

2 answers

0 votes

You can't.  "Done" is an Agile concept, not a field for a start, it's an indicator that something is completed.  The whole definition of a burndown chart is based on issues being "done", so if you changed it to something else, you don't have a burndown chart any more, you've got something telling you, well, nothing of any value.

Actually I've found that the burndown chart is triggered by dropping an issue into the rightmost column on the board.

It doesn't have to be named 'Done' and the status mapped to the column can be any state you want.

Yes, sorry, I should have pointed out that "done" really does mean "in the done column, on the far right", whatever it might actually be called

The resolution field needs to be set for the line to strike thought the issues (considered done) and the issue needs to be in the far right column.

 

if you are using the simplified work flow click the set resolution checkbox. 

Suggest an answer

Log in or Sign up to answer
Community showcase
Published Nov 27, 2018 in Portfolio for Jira

Introducing a new planning experience in Portfolio for Jira (Server/DC)

In the past, Portfolio for Jira required a high degree of detail–foresight that was unrealistic for many businesses to   have–in   order to produce a reliable long-term roadmap. We're tur...

2,979 views 19 22
Read article

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you