Hi all,

I'm a bit puzzled by the following EazyBi behavior:

My ticket as an original estimate, remaining estimate an actual work log

issue_time_tracking.PNG

But in my report I don't see remaining and original estimate values

ezbi_report.PNG

Is it a bug, or am I doing something wrong?

Thank you for your help.

J.

1 answer

1 accepted

0 votes
Answer accepted
Jerome Renaud August 27, 2015

Ooopppss found it, it's so silly that I ashamed to confess it : I also had a "time" filter somewhere so it's just causing the "issue". Sorry for the waste of time. 