Issues status set to 'done' but Jira handles as 'not completed'

Jay Pfeifer
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
April 6, 2022

I put all issues to the column "done" and also their status were set to "done". When I closed the sprint it says, all issues were not completed and I should move them to the next sprint or backlog. Also via board settings I checked that the "set resolution" is active.

 

Can anyone tell my how to fix that? Thanks!

 

jira2.PNG

1 answer

1 accepted

3 votes
Answer accepted
Callum Carlile _Automation Consultants_
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
April 6, 2022

Hi @Jay Pfeifer , welcome to the community!

Jira will only accept that your issue is 'Done' if it is in the last column of your sprint board when the sprint is ended (this is the 'Done' column, and you can only have one done column per board), so you will need to map your Done status to the final column via the board settings. You may need to map multiple statuses to this column if you have more than one 'done' status.

Hope this helps!

Jay Pfeifer
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
April 6, 2022

Ah I see! Thanks!

Callum Carlile _Automation Consultants_
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
April 6, 2022

No worries!

Richard Atkins
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
September 5, 2024

Thanks for this info @Callum Carlile _Automation Consultants_ this is finicky and your answer has resolved the same problem for us today :-) 

Suggest an answer

Log in or Sign up to answer