Issues are still showing up in my sprint

Bruno Mesquita dos Santos April 26, 2022

My team defined a time for our backlog (26/Apr/22 10:23 AM - 09/May/22 6:00 PM). But, when I go in the Sprint, it´s still showing old issue.

Does anyone know what the problem is?

2.PNG

 

11.jpg

 

12.jpg

1 answer

0 votes
Ivan Lima
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
April 26, 2022

You see the sprint start and end date, which neither filters the issues on the backlog view nor in the active sprint view. They are primarily used in reports that rely on the start/end date to calculate scope, velocity and burndown. Have you checked the issue history to understand when the issue was assigned to the sprint?