Issues Marked as Resolved are moving to new sprint each week

I have issues that have been marked as resolved/completed for the week that still move over to the following week's sprint.

1 answer

0 vote

The resolution does not matter when it comes to sprints.

My guess is that these issues were not "done" when you closed the sprint, meaning that they were not in the far right hand column of the board.  That's the bit that matters to Scrum

Thanks Nic but no dice. See screen shot below. Maybe I'm missing how something should be setup though.sprint screen shot.png

Suggest an answer

Log in or Sign up to answer
Atlassian Community Anniversary

Happy Anniversary, Atlassian Community!

This community is celebrating its one-year anniversary and Atlassian co-founder Mike Cannon-Brookes has all the feels.

Read more
Community showcase
Julia Dillon
Posted Tuesday in Jira

Tell us how your team runs on Jira!

Hey Atlassian Community! Today we are launching a bunch of customer stories about the amazing work teams, like Dropbox and Twilio, are doing with Jira. You can check out the stories here. The thi...

152 views 1 17
Join discussion

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you