Issue with sprint in JIRA

kA June 3, 2014

Hi,

I have faced the following issue on my agile board, Yesterday I have closed the sprint (Sprint 11) in agile board. But still I can see the sprint in open status in plan mode. But in the sprint report, it is mentioned as closed and there is no active sprint in work mode too. How can i recovered the problem, Please share your thoughts.

Thanks,

Karthik

1 answer

1 accepted

0 votes
Answer accepted
Luther Hargrove
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
June 3, 2014

Do you possibly have 2 sprints with the same name? I would check to see what the SPRINT ID is for the close and open one to see if you possibly have 2 that were named the same, but have a different backend ID.

Suggest an answer

Log in or Sign up to answer