I apologize for the lack of knowledge with proper terminology. I am new to JIRA.
If I change the Due Date on one issue, is it possible to have several other issues' Due Dates change automatically? So, several issues are dependant on the earliest Due Date issue. If this Due Date is pushed back, I would like all other issues' Due Dates to be pushed back the same amount time.
Thank you in advance for your help!
From what you said about sereval issues depending on the earliest due date issue, I assume you ate using JIRA issue links to mark that dependancy. It is not possible, without customization, to trigger a change on the due date of other issues when the due date on one issue changes.
Since you are on JIRA onDemand, you can't have customizations and so you are on a dead end.