Is there possibility to restrict Worklog creation for dates in the past

Alex Kiselev _Itransition_ July 7, 2013

example: there is monthly reporting process in company

during the first week on new month (july) time report for previous month (june) is created and analysed. If needs some people can add new Worklogs on june.

But there is a moment when time reporting for june dates should be freezed. It could be great if Manager could freeze time reporting for previous month.

Is there any suggestions?

Thanks in advance.

2 answers

1 accepted

1 vote
Answer accepted
Jobin Kuruvilla [Adaptavist]
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
July 7, 2013

Nope. You will have to do some plugin development if you need this functionality.

Another option is to move the issue to a new workflow state where the worklog permissions are revoked. That wouldn't need any development effort.

Renjith Pillai
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
July 7, 2013

I like this :)

0 votes
Viðar Svansson [Tempo]
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
July 7, 2013

Hi Alex,

Tempo Timesheets (commercial plugin) supports this. You can close (freeze) the month via the Period Management.

Cheers,
Viðar