example: there is monthly reporting process in company
during the first week on new month (july) time report for previous month (june) is created and analysed. If needs some people can add new Worklogs on june.
But there is a moment when time reporting for june dates should be freezed. It could be great if Manager could freeze time reporting for previous month.
Is there any suggestions?
Thanks in advance.
Nope. You will have to do some plugin development if you need this functionality.
Another option is to move the issue to a new workflow state where the worklog permissions are revoked. That wouldn't need any development effort.
I like this :)
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Alex,
Tempo Timesheets (commercial plugin) supports this. You can close (freeze) the month via the Period Management.
Cheers,
Viðar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.