Is there a way to sync portfolio if story changes epic link

Brian Keefe October 21, 2015

Scenario:

JIRA Project X has Epics and Stories

JIRA Project Y has Epics and Stories

Import filter to Portfolio Plan 1: project in (X, Y) - All epics and stories for X are under Initiative X (no JIRA issue linked) and same idea with Y. So "Epics" in Portfolio match exactly with actual Epics in JIRA, same with stories.

Boards are synced and everything looks good.

Product owner changes Story A's epic link from Epic Red to Epic Blue (this is done either by editing the story itself or dragging it on an agile board).

On Portfolio Plan 1, even after updating via "Update from date," the story still shows under Epic Red. Is there a way to have Portfolio automatically move that story based on the Epic Link field? Can anyone reproduce this behavior?

1 answer

1 accepted

2 votes
Answer accepted
Martin Suntinger
Atlassian Team
Atlassian Team members are employees working across the company in a wide variety of roles.
October 24, 2015

Hi Brian, this is currently not supported - there is an open suggestion ticket here https://jira.atlassian.com/browse/JPO-276 - we are working on addressing this as part of a general improvement of the integration with JIRA Software. 

Brian Keefe October 26, 2015

Just what I was looking for. Thanks Martin!

Daren Edmiston December 9, 2015

Thanks, that explains some issues we were seeing