Is there a way to set hours per day on a project basis?

Timothy Harris February 25, 2015

As far as I know, the hours per day setting is a global setting. There is an issue that has been raised for this but it has been sitting there for almost 9 years!

Really seems like basic functionality that is simply being ignored...

Is there any workaround for this?

We have teams that are using different working hours and need some type of solution, which is NOT to go out and buy another plug-in, i.e, Tempo Time Planner.

2 answers

0 votes
David Markowski (DO NOT USE) July 3, 2018

I have had this request too, has there been any update or workaround tools that could help with this? 

0 votes
Nic Brough -Adaptavist-
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
February 25, 2015

I'm afraid not, plain JIRA still has a single global hours-per-day setting.

The only workarounds are the ones you fear - install plugins that can handle it.