Is there a way to add more layers to the kanban board ?

Elijah Stownton April 22, 2021

I am trying to make a project that needs to have A completed, but A needs a sub task B to be done, which itself needs a few sub tasks done.

The hierarchy would be basically Project -> A -> B -> (C,D,E)

But Jira only lets me creates as far as B. Is there a way, a free one preferably, to do this ?

1 answer

1 accepted

2 votes
Answer accepted
Nic Brough -Adaptavist-
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
April 22, 2021

Jira Software's hierarchy is Epic -> Story -> Sub-task, there's no more layers in plain Jira. 

Advanced Roadmaps gives you layers above Epics, but there's no real way to do sub-tasks of sub-tasks in Atlassian software.

The Structure app does allow you to add more layers as well, you might want to take a look at that.