Hi there,
Considering i have a 3 steps workflow.
When i create issue, i enter estimated time, foe example 10 days.
When i use the first transition, whatever is the number of days, i need to set the remaining estimation to 50%
When at last, i closed issue, the remaining is set to 0 and in time tracking i got the 100% of logged work.
Is there any postfunction to customize?
Thanks a lot for your help.
You can use the "Set Field Value to constant or Groovy expression" (Script Runner add-on) post function for example.