Is it possible to set the time tracking per single jira project?

For our scrum boards we planned to use Original Time Estimate for team velocity.
Format that You enter the estimation is for example 6d5h which is evaluated to 6x8 hours + 5 hours = 53 hours For our internal estimation we use term "effective day" which is 6.5 hours of effective work (8 hours - time for lunch and other non-work related activities)


It is possible to change value of "number of hours per day"
The question is: Is it possible to set this value for one project only?

1 answer

This widget could not be displayed.

Hey Lynn.

The default time track in JIRA does not support this. I think you can try a time tracking plugin on Marketplace.

Suggest an answer

Log in or Sign up to answer
Community showcase
Posted Tuesday in Jira

What modern development practices are at the heart of how your team delivers software?

Hey Community mates! Claire here from the Software Product Marketing team. We all know software development changes rapidly, and it's often tough to keep up. But from our research, we've found the h...

93 views 1 2
Join discussion

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you