Hi,
Is following possible in Jira to set up and track for the project and task?
1. Work Assigned Date.
2. Work Completed Date.
3. Billable Hours
4. Non-Billable Hours
5. Project Wise Hours Report or Billable VS Non-Billable.
6. Report Of total team Hours Paid by Firm Per Month VS Approved Hours Paid by Client.
7. Project-wise planned tasks for the next 30_60_90 days.
8. Team Resource Calendar.
1-5 and 7, yes.
6 is possible with some coding and config, but you'll find it far easier to get an app to do most of it for you. Tempo for example will provide reporting that are specifically aimed at doing point 6 as well as providing a planning function and helping with most of the other points.
8 - definitely not off-the-shelf, you'll need an app. Again, I think there are functions in Tempo that can help, but don't quite do what I'd like to see in a resource calendar