A team works in scrum board and sub tasks that were completed in the previous sprint will be dragged with their uncompleted Story to the current sprint - that's OK.
Now - if I search
or
the sub task will appear in both.
If I want to get a report / JQL of how much work was completed in a sprint, in which sprint will that sub task appear in?
I'm trying to understand how Jira refers to that sub task vs. the sprints he's in.
Thank you!
Ayelet
The sub-task's work was completed in the sprint in which its parent was completed. That is how sprints work - you don't say you've finished a piece of work until you have. Any partial work done in previous sprints is unimportant because scrum measures achievement, not progress towards it.