In portfolio, is there a way to plan with team velocity increasing over time?

Nicolas Gendron April 19, 2017

I'm using portfolio for our Roadmap which meant that the scope I'm playing with covers multiples years.

I would like to know if this is possible to have the team velocity increase over time ... let say, 10% each year.

 

1 answer

0 votes
Thomas
Atlassian Team
Atlassian Team members are employees working across the company in a wide variety of roles.
November 19, 2017

Hi @Nicolas Gendron,

 

This is currently not supported directly but as a workaround if you are using time planing I'd suggest having a look at exceptions which allow to define a team member weekly capacity over a specific period of time.

 

Also I've created a feature suggestion for Portfolio for Jira server here: JPOSERVER-2044

 

Cheers,

Thomas.