In Version Workload report , sub-task time estimate is not rolling up into story estimate

In Version Workload report I have one story with 2 subtasks.

Subtasks estimates show but story shows as No Estimate.

I thought the time estimates should roll up. Doesns't it?

2 answers

No, the workload report is grouped by asignee rather than story.

I cannot believe that this does not work.  What is the point of estimating subtasks and not have them roll up into the parent task in any point of estimates being provided.  We are completely blocked by not having sub-tasks roll up in the sprint planner.  I am flabbergasted that this is not more well thought out.

Suggest an answer

Log in or Sign up to answer
Community showcase
Published Jan 08, 2019 in Jira

How to Jira for designers

I’m a designer on the Jira team. For a long time, I’ve fielded questions from other designers about how they should be using Jira Software with their design team. I’ve also heard feedback from other ...

1,266 views 5 10
Read article

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you