In Tempo, can I set the hours required to 0 for all users?

JIRA v4.4.4

TEMPO v6.5.1.3

We want to essentially turn off the required hours - I think this is done by setting minimum hours required down to 0. Is there a way to do this for all users at once?

1 answer

Hi Greg,

yes, you can set required hour to 0 but you cannot do this for all users at once. It gets easier in Tempo 7.5 where you can create workload schemes for users. If you edit them you can do it for everyone in scheme at the same time.

Best regards

Susanne (Tempo)

He is using JIRA 4.4 so he uses the user properties table to configure required hours. I guess it would be possible to create a SQL query to update it for all users at once.

Suggest an answer

Log in or Sign up to answer
How to earn badges on the Atlassian Community

How to earn badges on the Atlassian Community

Badges are a great way to show off community activity, whether you’re a newbie or a Champion.

Learn more
Community showcase
Published Thursday in Jira

5 ways you can make the most of Jira Software and Bitbucket Cloud

As part of the Bitbucket product team I'm always interested in better understanding what kind of impact the use of our tools have on the way you work. In a recent study we conducted of software devel...

118 views 0 5
Read article

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you