In Review issues appearing as complete

When looking at the Sprint Report for our current sprint, the In Review issues are showing as in the Completed Issues section. The resolution is unresolved. Why is this?

1 answer

This widget could not be displayed.

Hi Teal, 

Sprint Report is based on To Do and Done statuses independent of the resolution. 

Also, according to the documentation:

Please note that, the mapping of statuses to your board determines when an issue is considered "To Do" or "Done". See Configuring Columns for more information.

Perhaps you can use this workaround to properly set the resolution once your issues are done.

Please let us know if this answers your question.

Cheers!

Suggest an answer

Log in or Sign up to answer
Community showcase
Posted 5 hours ago in Jira

What modern development practices are at the heart of how your team delivers software?

Hey Community mates! Claire here from the Software Product Marketing team. We all know software development changes rapidly, and it's often tough to keep up. But from our research, we've found the h...

19 views 0 1
Join discussion

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you