In Review issues appearing as complete

Teal Nissley September 25, 2014

When looking at the Sprint Report for our current sprint, the In Review issues are showing as in the Completed Issues section. The resolution is unresolved. Why is this?

1 answer

0 votes
Elisa [Atlassian]
Atlassian Team
Atlassian Team members are employees working across the company in a wide variety of roles.
September 25, 2014

Hi Teal, 

Sprint Report is based on To Do and Done statuses independent of the resolution. 

Also, according to the documentation:

Please note that, the mapping of statuses to your board determines when an issue is considered "To Do" or "Done". See Configuring Columns for more information.

Perhaps you can use this workaround to properly set the resolution once your issues are done.

Please let us know if this answers your question.

Cheers!