In Portfolio the member on a story is not updated when the assignee is changed in JIRA.

If I change the member in Portfolio on a story, then the assignee is changed in the story in JIRA.  If I change the assignee in the Story in JIRA the member is not changed in Portfolio.  This seems inconsistent.  Is this a bug?

2 answers

looks like.

@David Freedman3

I think you are facing issue in case:

When we change the assignee from Portfolio it will be reflected on JIRA. But now when we change assignee again from JIRA for the same story then it will not be reflecting on Portfolio after recalculating plan.

If YES then the solution is here:
For this we just go to the Members column of that story -> click on the member -> a menu get opened -> click on "Clear selected items" -> Click on "Apply"  -> Now commit the changes
Now assignee will get changed.

 

Above process is feasible if number of items are less but this process might become lenghty If we do have many items.

Suggest an answer

Log in or Sign up to answer
Community showcase
Published Nov 27, 2018 in Portfolio for Jira

Introducing a new planning experience in Portfolio for Jira (Server/DC)

In the past, Portfolio for Jira required a high degree of detail–foresight that was unrealistic for many businesses to   have–in   order to produce a reliable long-term roadmap. We're tur...

2,419 views 15 19
Read article

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you