In Active sprint, display sub-task which is under parent

Tuan Lam April 17, 2017

Hi all,

In Active sprint, we have Story A with 2 sub-task as below:
=====================
Story A
      Sub-task 1 (implement)   -> Member B
      Sub-task 2 (testing)  -> Member C
=====================

We have quick-filter (assignee = Member C).
Current: When clicking on quick-filter, Sub-task2 will be displayed
Expect: When clicking on quick-filter, Sub-task1 and Sub-task2 will be displayed but Sub-task2 will in White-background and Sub-task1 will be in Gray-background

Business need: We need this because sometime when implement a sub-task1, we need to know status of sub-task2 and for knowing this, we MUST click on StoryA to see status of subtasks

 

Currently, we are using sub-task and filter tasks (belong to each members) by quick-filter (assignee = <name>).

The problem is: when choosing 

1 answer

0 votes
Nic Brough -Adaptavist-
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
April 17, 2017

Your quick filter specifically excludes sub-task 1.  That's what you have built it to do.

You will need to create a quick-filter that includes the other sub-task instead of dropping it.

Tuan Lam April 17, 2017

Thank for your reply. How can i do that?

Tuan Lam April 17, 2017

I mean query for quick filter will be changed from "assignee = <name>' to ??