If a sub-task has time logged against it, if it should can automatically be put into the "In Progress" state?

Wu Jun July 27, 2014

My question is : If a sub-task has time logged against it, if it should can automatically be put into the "In Progress" state?

1 answer

0 votes
Nic Brough -Adaptavist-
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
July 27, 2014

You'll need to find or write a listener to catch the "work logged" event and automatically transition the issue.

I think you're out of luck though - you can't install these on OnDemand and I don't think there's one on the list of approved plugins.

Wu Jun July 27, 2014

Ok ,thanks.