I would like to burn down points throughout the sprint instead of tracking time spent.

This question is in reference to Atlassian Documentation: Configuring estimation and tracking

Is it possible to generate a burndown chart based on points being spent each day instead of tracking time in hours?

1 answer

I'm not sure what do you mean by "Points being spent each day" but there are 2 configurations for the JIRA Burndown chart for Time Tracking.

One is the by "Remaining Estimate and Time Spent" and the other one is by "Issues will burn down their Story Points value upon completion"

Configure your board then open the "Estimation" tab to see this configs.

It looks like I want to use "Remaining Estimate and Time Spent" since I want it updated daily instead of upon completion of the story. But I'd like to record the "Remaining Estimate" as story points, not hours or minutes.

Suggest an answer

Log in or Sign up to answer
Community showcase
Published Nov 27, 2018 in Portfolio for Jira

Introducing a new planning experience in Portfolio for Jira (Server/DC)

In the past, Portfolio for Jira required a high degree of detail–foresight that was unrealistic for many businesses to   have–in   order to produce a reliable long-term roadmap. We're tur...

2,299 views 12 19
Read article

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you