I was able to move a Story from Analysis to Completed even when ALL the Sub-Tasks were NOT completed.

I have defined a separate workflow for Story and Sub-tasks. My workflow for Story is as below

(Open-> Analysis-> Developement-> QA-> Completed-> Release) 

 and for Sub-Tasks it is as below

(Open-> Assigned-> InProgress-> OnHold-> Completed) 

 

I was able to move a Story from Analysis to Completed even when ALL the Sub-Tasks were NOT completed. Why is that so?

 

I donot want my Story to get completed unless all of its associated Sub-Tasks are Completed. Need help.

Regards,

Ashwin

 

2 answers

Thank You Chris

That was helpfull.

 

 

Suggest an answer

Log in or Sign up to answer
Atlassian Community Anniversary

Happy Anniversary, Atlassian Community!

This community is celebrating its one-year anniversary and Atlassian co-founder Mike Cannon-Brookes has all the feels.

Read more
Community showcase
Julia Dillon
Posted Tuesday in Jira

Tell us how your team runs on Jira!

Hey Atlassian Community! Today we are launching a bunch of customer stories about the amazing work teams, like Dropbox and Twilio, are doing with Jira. You can check out the stories here. The thi...

741 views 1 18
Join discussion

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you