We are currently using Jira 6.4 version. I can see either the burndown as per story points or through time spent.

 

Is there a way to see both in the same burndown?

1 answer

0 votes
Suhas P
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
September 8, 2017

I don't think that is possible with out of the box burndown feature. You can use Dashbord gadget Sprint Burndown to see the two different charts at the same time. But for this you need to use two different boards with different estimation option one board with Estimation statistic based on Story point and other with Time spent for same sprint.