I simply can't get an issue to be "resolved"

Alex Markov April 30, 2017

So here is my workflow: http://imgur.com/a/K4I9R

And I have this issue: http://imgur.com/a/LH2ay

The problem I am having is that this issue is still in the "unresolved" state (red arrow). I've been able to update my workflow so that I have a Post Function that automatically resolves issues when they get into the the "done" staging going forward. However this issue is already there and I can not move back backwards and forwards into this "done" stage again where this Post Function would be triggered. So now I am stuck with this issue in all of my reports just sitting there, even though work was completed on it a week ago. :-/ 

Can anyone help?

1 answer

1 vote
Nic Brough -Adaptavist-
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
April 30, 2017

Your workflow doesn't have any way to move back from "ready" or "done".  I would add routes back, even if they're limited to the project lead or admins only.

For issues that are now stuck without a resolution and can't be pushed back, you have several options, but I would go with one of the more obvious ones:

  • Edit the workflow to allow a move back, then re-do the close (as you've added a post-function to set the resolution)
  • Add a transition that does not change the status, but does include the post-function to set the resolution
  • At a *very* quiet time for your users, add the Resolution field to the "edit" screen, search for "status in (done / deployed, ready for deployment) and resolution is empty", and use bulk-edit to set a resolution.  Then remove the field before your users trash your data.