We have estimated the whole backlog in Stroy points.Is there a way of totalling it up in the Plan mode?

1 answer

1 accepted

1 vote
Accepted answer

Create a sprint (no need to start it) and drag the marker to the end of the backlog. The totals will appear in the sprint marker. Delete the sprint when you have your answer if you don't need it.

Suggest an answer

Log in or Sign up to answer
Community showcase
Published Nov 27, 2018 in Portfolio for Jira

Introducing a new planning experience in Portfolio for Jira (Server/DC)

In the past, Portfolio for Jira required a high degree of detail–foresight that was unrealistic for many businesses to   have–in   order to produce a reliable long-term roadmap. We're tur...

2,772 views 18 21
Read article

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you