I have a requirement to have the following structure: in Kanban Swim Lanes

Kamlesh Solanki July 29, 2021
  • Project
    • Epic
      • Story 1
        • Task 1
        • Task 2
        • Task 3
      • Story 2
        • Task 1
        • Task 2
        • Task 3
      • Story n
        • Task 1
        • Task 2
        • Task 3
      • Epic
        • Story 1
          • Task 1
          • Task 2
          • Task 3
        • Story 2
          • Task 1
          • Task 2
          • Task 3
        • Story n
          • Task 1
          • Task 2
          • Task 3
        •  

Each story should be assigned to a different team member

 

There are numerous projects

 

1 answer

0 votes
Bill Sheboy
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
July 29, 2021

Hi @Kamlesh Solanki -- Welcome to the Atlassian Community!

I do not believe there is anything in out-of-the-box Jira Cloud with that level of nesting for swimlanes on a board.  For a company-managed project, the closest things might be:

  • Swimlane on stories and use a board filter which orders by project and epic
  • Swimlane by queries, and create as many queries as you need for the specific lanes.  This would require updating the swimlane queries manually.

Best regards,
Bill