How to set original estimate (time) to Issue?

Evgeniy Nechayev November 11, 2016

I do not want to use Scrum, I do not want to use Agile. I want to set Time Estimation for issue and using Time tracking only. 

How to add Original Estimation field to Issue creation screen?

1 answer

1 vote
Nic Brough -Adaptavist-
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
November 11, 2016

Add the field called "time tracking" to the issue create screen (you can find it by working down through the project's "issue type screen scheme")

Kamal Kailasa Babu April 20, 2020

how to bring this "time trcking" field?

Suggest an answer

Log in or Sign up to answer