How to restrict maximum time planning per day up to 8 hours using Tempo Timesheets?

Kirill Skuybida January 21, 2016

Hi all,

We're facing an issue that sometimes PM can plan more than 8 hours/day for developers. Is there any way to limit this?

 

Thanks!

2 answers

0 votes
Alexander Eck January 21, 2016

Kirill,

it is possible to plan an employee more than the workload per day. However all overload is displayed/underlined in red and is indicated in the capacity report.

Regards

0 votes
Dennis Poort January 21, 2016

Tell the PM to be realistic when planning. wink

 

You can define the maximum amount of hours to be registerered in timesheets, but as far as I know this only limits logging hours, not planning them.

Personally I like being able to overplan sometimes. The planning view does show the amount of hours that remain available on the day, so I consider this PM responsibility.