How to properly set time tracking on a new Scrum Board? (It seems to be bugged)

I do not see the Estimate fields, even though I set my project to estimate by time.

I simply cannot see the fields anyways, no one in my team can.

When I attempt to create an issue it says that I need to set the Original Estimate though there's no field for it in the creation form.


Thanks 

2 answers

This widget could not be displayed.

Maybe the estimate fields are not present on the create issue screen associated with your stories?

This widget could not be displayed.

Reached a point where this was SO bugged I could estimate but numbers wouldn't show up on the cards list. Finally deleted the project and started brand new.

weird 

Suggest an answer

Log in or Sign up to answer
Atlassian Summit 2018

Meet the community IRL

Atlassian Summit is an excellent opportunity for in-person support, training, and networking.

Learn more
Community showcase
Posted Wednesday in New to Jira

Are you planning to trial, or are currently trialling Jira Software? - We want to talk to you!

Hello! I'm Rayen, a product manager at Atlassian. My team and I are working hard to improve the trial experience for Jira Software Cloud. We are interested in   talking to 20 people planning t...

131 views 2 0
Join discussion

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you