Currently Team value for Sub-task is inherited from parent Story/Task
Is there a way to set Team value of Sub-task to be different than the one set on parent Story/Task?
Of course by also keeping Portfolio calculation working.
Hey Francesco,
(I believe) you are not able to have Sub-Tasks assigned to different Teams in Portfolio, if they do manage to inherit different teams Portfolio will throw an error.
Tyler
Yes this makes no sense and is not a real world scenario. You can have a user story that has subtasks assigned to different teams yet Portfolio seems to not want to digest.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Tyler,
Thanks for the answer, I guess we will have to find a different solution then.
Best,
Francesco