How to prevent Portfolio Team value for Sub-task to be inherited from parent Story/Task?

Currently Team value for Sub-task is inherited from parent Story/Task

Is there a way to set Team value of Sub-task to be different than the one set on parent Story/Task?

Of course by also keeping Portfolio calculation working.

2 answers

This widget could not be displayed.
Tyler Brown Community Champion Nov 24, 2017

Hey Francesco,

(I believe) you are not able to have Sub-Tasks assigned to different Teams in Portfolio, if they do manage to inherit different teams Portfolio will throw an error.

Tyler

Yes this makes no sense and is not a real world scenario.  You can have a user story that has subtasks assigned to different teams yet Portfolio seems to not want to digest.  

This widget could not be displayed.

Hi Tyler,

Thanks for the answer, I guess we will have to find a different solution then.

Best,

Francesco

Suggest an answer

Log in or Sign up to answer
Atlassian Summit 2018

Meet the community IRL

Atlassian Summit is an excellent opportunity for in-person support, training, and networking.

Learn more
Community showcase
Posted Wednesday in New to Jira

Are you planning to trial, or are currently trialling Jira Software? - We want to talk to you!

Hello! I'm Rayen, a product manager at Atlassian. My team and I are working hard to improve the trial experience for Jira Software Cloud. We are interested in   talking to 20 people planning t...

146 views 2 0
Join discussion

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you