Hello,
I have a few questions
Let`s assume I have 2 user stories with the following estimates
US1 - 16 ideal hours
US2 - 8 ideal hours
and I know that a team could cover 8 ideal hours of work per day.
Is there an add-on or any other way to predict release date in form of burndown chart in Cloud Jira for the following cases
1. If everything is fine. In this particular case, It would be in 3 days.
2. If estimates for US2 changed from 8h to 16h during the development, I would like to see the original date(3 days) and the new one(4 days)
Regards