How to obtain metrics on scope change and sprint rollover for the cloud version of Jira

If I obtain Scriptrunner for the cloud will that provide what I am looking for?  I need to see the adds/drops within the sprint as well as the work that was moved out of the sprint (rollover) at the end of the sprint.

1 answer

0 votes
Tyler Brown Community Champion Jan 10, 2018

Hey Michelle,

You should be able to use the Reports section on a board to see this information.

If you go to the Sprint Report it will show you all issues that were completed, not completed and removed from any given Sprint.  It will also put a "*" beside and issue that was added to the Sprint after it was started.  

You can also select to view all this information in the Issue Navigator which will give you a filter for all the relevant issues.

Hope this helps,

Tyler

Thank you for your reply, however, I am trying to export this information.  If viewed in navigator the scope change details are lost.  It also does not show rollover from one sprint to another.  I've seen that Scriptrunner can provide this details, however, it's not clear to me if the cloud version of scriptrunner will also provide this information.

Suggest an answer

Log in or Sign up to answer
Community showcase
Posted Sep 18, 2018 in Jira

What modern development practices are at the heart of how your team delivers software?

Hey Community mates! Claire here from the Software Product Marketing team. We all know software development changes rapidly, and it's often tough to keep up. But from our research, we've found the h...

26,403 views 2 7
Join discussion

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you