Hi all,
I have a jira (v7.3.7) and portfolio (v2.2.6), I am looking for mapping these two with each other.
I have certain issues in jira which I want to see on portfolio automatically
I have followed this link, but there is no "synchronization" option available.
also, i enabled "commit of changes" to "ON" in portfolio plan configuration but no luck.
Is there any way to do automatically sync complete jira issue with portfolio and vice versa.
Thanks in advanced
That link looks to give instructions for Classic Plans, it sounds like you are using the new ones. Issues created in JIRA should automatically come into your Portfolio plan, but can depend on a couple of things:
Is the problem you can't see the issues at all or just a limited view of them?
Hi Steven, Thank you for your reply
Issues from jira are sync with portfolio plan but I did not see the complete issue getting synced with the portfolio. some fields like "assignee".
so how can I map "assignee" from jira issue into the portfolio
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.