How to make Jira set original estimate to 0 when task is FIXED?

Uing new Jira board (non classic one)

I found strange behaviour of sprint bundown chart, it shows also DONE tasks original estimates, as if nothing is closed.

Checked the log under the burndown chart and found that as soon as I manually set "Original estimate" to 0 for done tasks hours Burndown starts showing correct state of the sprint.

Two questions:

1. Not sure this is correct (as if original estimate is set to 0 historical data how much it was is gone)?

2. If this is the only way to get correct burndown, how setup Jira in the way to drop original estimate to 0 as soon as task is set to DONE.

Thanks for your help in advance,

Aquarius.

1 answer

1 accepted

Suggest an answer

Log in or Sign up to answer
Atlassian Community Anniversary

Happy Anniversary, Atlassian Community!

This community is celebrating its one-year anniversary and Atlassian co-founder Mike Cannon-Brookes has all the feels.

Read more
Community showcase
Julia Dillon
Posted Tuesday in Jira

Tell us how your team runs on Jira!

Hey Atlassian Community! Today we are launching a bunch of customer stories about the amazing work teams, like Dropbox and Twilio, are doing with Jira. You can check out the stories here. The thi...

211 views 1 18
Join discussion

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you