How to link existing Jira tickets in porfolio 2.0

Hello,

With the new JIRA porfolio if i create "Scope" items but not commit them, is there any way to link the items to existing JIRA tickets?  Old potfolio lets you do this and in new one, i don't see a way and once you commit, it forces you to create a new ticket id, so now i have dupes.

Any ideas?

Thank you

1 answer

0 votes
Hey Roman, 
It is partly possible to link uncommitted issues to JIRA tickets depending on what your intended use case is. 
if you intend to create an association link (e.g relates to) between an uncommitted issue and an existing JIRA ticket then this isn’t possible. Uncommitted issues don’t actually exist as issues in JIRA and therefore cannot be linked through JIRA.
If you want to create a dependency link (similar to 'required by’ in old portfolio) then you can add a dependency link in Portfolio between an uncommitted issue an existing one in JIRA. When you calculate your plan it will accommodate the dependency link. Note that this link will not be integrated with JIRA until you commit the issue creation and the dependency link in Portfolio.
You can do this by clicking the issue key and adding a dependency to the issue detail view.

Suggest an answer

Log in or Sign up to answer
Community showcase
Posted Oct 16, 2018 in Jira

Looking for anyone who made the switch to Data Center

The Jira Marketing team is putting together an ebook on migrating to Data Center. We're looking for pro tips on how you staffed your project team and organized your Proof of Concept. Share yo...

77 views 0 3
Join discussion

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you