Andre Borzzatto
Atlassian Team
Atlassian Team members are employees working across the company in a wide variety of roles.
March 24, 2015

Hi Hayley,

We would like to inform you that mapping the sprint number isn't possible in JIRA when importing via CSV. However, there's a feature request which has been raised for this functionality. For your reference, please see https://jira.atlassian.com/browse/GHS-5942.

Atlassian is not planning to implement this feature in the next 12 months but we are encouraging you to add the ticket on your watch list and vote for the ticket as well to receive future updates and increase its popularity.

Hope it helps.

Regards,

Andre

0 votes
Dionisio Gomes May 23, 2017

There is an alternative way to accomplish this task. In the sprint field of the csv file instead of adding the sprint number 0, 1, 2, 3 ... add the sprint id (this number you can get in the database in the sprint table).

0 votes
Hayley Hinkle March 24, 2015

Thanks for answering. This is very disappointing though because it makes it difficult to move from Rally (our current tool) to Jira.

0 votes
Hayley Hinkle March 23, 2015

I created the sprint previous to the import, but it said the sprint did not exist. Help!!

Suggest an answer

Log in or Sign up to answer