How to display subtasks under issues on a sprint board

Currently we are using a sprint board and would like to display subtasks under our issue's I've seen this done before but do not know how to configure it. We are using the cloud version of Jira.

1 answer

0 votes

Just make sure the board includes the subtask types and then try setting the swimlanes to "stories"

(You won't see them in planning, because you don't need them there, but they'll appear on the working view of the board)

I did configured my board to have Stories swimlanes; however, the subtasks are not showing on the sprint board. What am I doing wrong?

Suggest an answer

Log in or Sign up to answer
Community showcase
Posted Sep 25, 2018 in Jira

Atlassian Research Workshop opportunity on Sep. 28th in Austin, TX

We're looking for participants for a workshop at Atlassian! We need Jira admins who have interesting custom workflows, issue views, or boards. Think you have a story to sha...

422 views 7 5
Join discussion

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you