I am trying to add a gadget into my projects dashboard to show the percent completion bar of all the subtasks per issue I have in my active sprint. It should give me a good summary of the overall statuses of all issues in the active sprint without having to go into the project itself and clicking on each issue individually.
Is there any existing gadget that can display this information? what configuration and setting do I need to select.
I tried using the Issue Statistics and the Filter Results, but I was not successful in getting the results I wanted. In the Filter Results gadget there is a n option to select progress, however when I select that option, there is no information displayed.
Hi @David.Newton,
Yes. You can do this with our Great Gadgets app for Jira. One of the many gadgets that this plugin offers is the Advanced Issue Filter Formula Gadget that you can use to calculate the percent completion of your subtasks.
Here is on how to configure the gadget:
If you need any help, please contact support@stonikbyte.com.
Danut
Hi @David.Newton.
Welcome to the community, @Dylan.Martis.
With our Jira cloud app Dynamic Custom Fields for Jira you can create a custom field that calculates the percentage of the completed child issues.
We offer a template for your use case: "Completed child issues percentage".
Dynamic Custom Fields can be used as any other issue fields in your dashboard gadgets.
If you have feedback or questions, don't hesitate to contact us.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello David,
Thanks for reaching out to Community!
Allow me to step in just to share with you that currently, there are no native functionalities in Jira that allow viewing the percentage of the sub-tasks progress on a gadget.
There was a feature request suggesting this, but it was closed as “Won’t do”:
The best option, in this case, is to use an add-on as suggested and if you have any questions while testing the options, you can reach out to their support directly.
Kind regards,
Angélica
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Yeah this is the highest demand is to see the %, seems pushing us back to use less and less of JIRA unfortunately. not sure when this can be available
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello David and welcome to the Community!
Your question is similar to a few others which have been asked within Community, take a look at these other posts to see if they help you with your solution:
Additionally, we have further documentation that can be found at Monitor the progress of a sprint.
Regards,
Stephen Sifers
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
When using any of this functionality, does this roll up and aggregate into the actual percent complete for an issue?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.