How to auto set duedate by priority when create a issue

I want to achieve this function, when create a bug, the duedate will be auto set.
If priority = S, duedate will be set to this day +3 days

If priority = A, duedate will be set to this day +5 days

If priority = B, duedate will be set to this day +8 days

If priority = C, duedate will be set to this day +10 days

How to do this?

Thanks very much!

2 answers

This widget could not be displayed.

You'll need a bit of code to do this.  I'd write a post-function (using the Script Runner) to set the date after the user posts the creation.

This widget could not be displayed.

An alternative to programming is to use an Update issues post function for each of the cases and condition the post function by using %original_priority% equaling the value. For the due date field, use a specific value of %now% and add the + days in the Due date offset in days field. You may need to be careful with date format,  Substitution variables has more on that.

Suggest an answer

Log in or Sign up to answer
Community showcase
Posted yesterday in Jira

What modern development practices are at the heart of how your team delivers software?

Hey Community mates! Claire here from the Software Product Marketing team. We all know software development changes rapidly, and it's often tough to keep up. But from our research, we've found the h...

34 views 0 1
Join discussion

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you