How to analyse the Graph In Sprint report

YM August 3, 2015

Hello Team,

 

I have Quick question to ask.

 

I am bit confused with graph in Sprint report

image2015-8-4 12:58:21.png

 

Can any one of you please explain the above graph,

1)what does Red line,Green line and Grey Line Indicate here.

2)why is the Red line started from the top? and why is it decreasing ?

3)what does Grey line indicate,why is it started from Top and Gradually decreased

 

Thanks,

Yogashree.M

5 answers

0 votes
Sateesh Chandra
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
August 4, 2015

Guide line means the optimal way the sprint progresses. The Estimate decreases consistently, stabilizes at few instances and then reach zero at the end of the sprint (last day of sprint)

 

0 votes
YM August 4, 2015

Hey Sateesh,

 

Thanks you so much for the response.

 

But Grey what kind of guide line it would provide ?

 

Thanks,

Yogashree.M

0 votes
Sateesh Chandra
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
August 4, 2015

Redline - remaining values.

Grey - provides guideline for the progress

Greenline - progress of the sprint

 

It provides the correct data after the sprint completion

siva July 31, 2019

Hi sateesh,

can we show data of sprints in the graphs.?

0 votes
YM August 4, 2015

Hello,

We are using 6.3.6 version, and also i was talking about Green Line.

what does green Line indicate?


And also Grey is an ideal line,can you please justify how is it?


Appreciate a quick response


Thanks,

Yogashree.M

0 votes
Sateesh Chandra
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
August 3, 2015

Red line explains how the Story points are actually burnt (in your case team hours)

Grey line is is ideal line for comparison with the Red line.

 

I dont see a Red line. Which version of JIRA Agile are you using

Suggest an answer