How to account for regression testing in a portfolio plan.

As a team we are new to using portfolio for JIRA and have a few things that have come up that we need a bit of advice on.

One of those is Regression testing and how to add that into the plan to sit at the end of the dev work.

We have added as a task just called "regression" for now but wanted to know if anyone includes regression and how this is done?

Thanks

1 answer

0 votes

Hi @Lucy Richardson,

 

You could use Stages and estimations which I believe would be a good fit for your use case. See more

 

Cheers,

Thomas

Suggest an answer

Log in or Sign up to answer
Community showcase
Published Nov 27, 2018 in Portfolio for Jira

Introducing a new planning experience in Portfolio for Jira (Server/DC)

In the past, Portfolio for Jira required a high degree of detail–foresight that was unrealistic for many businesses to   have–in   order to produce a reliable long-term roadmap. We're tur...

2,790 views 18 22
Read article

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you