How to Edit Original Estimates Properly?

Batuhan Durmaz May 15, 2024

Greetings,

We have multiple projects on Jira.

The working hours of these projects are between 09:00-19:00 (10 hours)

However, in some of our projects 8 hours = 1 day on clockworks, while in some projects 10 hours = 1 day.

How can I organize this ambivalence? Where can I edit it?

1 answer

1 accepted

0 votes
Answer accepted
Ivan Lima
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
May 15, 2024

Welcome to the Atlassian Community.

The time tracking is global and affects all projects. If you need different configurations for different projects, you will need to manage this through other mechanisms like custom fields or third-party plugins that allow project-specific time tracking settings. See https://support.atlassian.com/jira-cloud-administration/docs/configure-time-tracking/ for more details.

Batuhan Durmaz May 17, 2024

Thank you.