How should I track development and test time estimates/effort?

I'd like to be able to start using the time tracking capabilities in JIRA. But my concern is that I see no way to separate out the development vs. the test time. There is only one Original Estimate field - who should fill it out? Should it include both the development and test time? Is there any good way to capture dev and test effort independently? I'd really like to know how other groups do this - please share your experiences.

Thanks,

Jason

1 answer

Jason,

You have quite a few options to accomplish most of your needs:

Development vs. Test time:

There are 2 plugins available in JIRA Extension Page which might be able to fulfill the requirement:

Developement vs. Test time effort independently:

You can either use jira reports or different transitions on the workflow and even different plugins:

I hope it helps you! :)

Suggest an answer

Log in or Sign up to answer
Community showcase
Published Nov 27, 2018 in Portfolio for Jira

Introducing a new planning experience in Portfolio for Jira (Server/DC)

In the past, Portfolio for Jira required a high degree of detail–foresight that was unrealistic for many businesses to   have–in   order to produce a reliable long-term roadmap. We're tur...

2,559 views 15 21
Read article

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you