How many sprints can I run in Paralel

James Spencer February 20, 2014

Hi

I am using JIRA Agile on demand and using Agile and want to run multiple sprints at the same time using the same product backlog, I have the labs add on setting set for paralel sprints enabled but wanted to know how many sprints I can run at the same time, is this limited to 2 or more?

r

James

1 answer

1 vote
Benito Picarelli
Atlassian Team
Atlassian Team members are employees working across the company in a wide variety of roles.
February 20, 2014

Hi james, how you doing?

When Parallel Sprints are checked you can start as many as you'd like to. Also, keep in mind that if you un-check the option, the sprints that have been started already will continue normally, but you won't be able to start more than one at the same time.

Benito