Coming from Planning Board I am a bit confused how (Rapid) Board works when planning sprints.
Before:
New flow?
It's the last step that I am uncertain of. Is that the normal workflow, to remember to manually change fix-version for all the issues?
Is there no connection between the field "fix version" and Greenhopper's field "Sprint"?
I found the answer in Atlassian's GreenHopper User Guide. In "Ending a Sprint" it states:
Many Scrum teams don't release a version at the end of a sprint, but if you need to, it's easy to do. In theCompleted Issues section of the Sprint Report, just click View in Issue Navigator. You can then use JIRA's Bulk Edit to assign all of the issues to the relevant version (for details, please see the JIRA documentation on Bulk Operations).